ProjeQtOr free project management software - [SOLVED] Problem with planned end date - ProjeQtOr
 

[SOLVED] Problem with planned end date

More
22 Jun 2017 16:11 #1 by #Chris
Hello,

I have planned a project which should have started last year in August. The validated start date was 22/08/2016 and the end date 30/09/2016. But now we could only start at 13/06/2017. So I set the project on ‘in progress’ on 13/06/2017 but didn’t change the validated dates. The program changed the planned date to the actual start date but didn’t change the planned end date. So I got an error note because the planned end date is before the start date. But now I can’t change anything. Is this a bug or is it my mistake? What can I do?
Enclosed I send you a screenshot of the problem. As you can see the gantt chart is right.

Thanks you very much for your help! :)
Attachments:

Please Log in or Create an account to join the conversation.

More
22 Jun 2017 19:06 #2 by babynus
Just run planning calculation to fix this.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
23 Jun 2017 11:45 - 23 Jun 2017 11:48 #3 by #Chris
I did it already. So the bar in the gantt chart has 'slipped' to the correct date. But the written planned end date in the activity didn't change.
And I also cann't change the validated end date to the future now. (see file attached)
Attachments:
Last edit: 23 Jun 2017 11:48 by #Chris.

Please Log in or Create an account to join the conversation.

More
23 Jun 2017 14:03 #4 by babynus
Are you using latest V6.2.5 ?
(if not, consider migrating)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
23 Jun 2017 17:37 #5 by #Chris
Yes, we use already V6.2.5
Do you need any more niformation?

Please Log in or Create an account to join the conversation.

More
27 Jun 2017 23:52 #6 by babynus
From what I can see on screenshot, you don't have assigned work.
Try and add at least 0,1 assigned work and replan (then you can remove added work if you please)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.041 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.