I have planned a project which should have started last year in August. The validated start date was 22/08/2016 and the end date 30/09/2016. But now we could only start at 13/06/2017. So I set the project on ‘in progress’ on 13/06/2017 but didn’t change the validated dates. The program changed the planned date to the actual start date but didn’t change the planned end date. So I got an error note because the planned end date is before the start date. But now I can’t change anything. Is this a bug or is it my mistake? What can I do?
Enclosed I send you a screenshot of the problem. As you can see the gantt chart is right.
I did it already. So the bar in the gantt chart has 'slipped' to the correct date. But the written planned end date in the activity didn't change.
And I also cann't change the validated end date to the future now. (see file attached)
From what I can see on screenshot, you don't have assigned work.
Try and add at least 0,1 assigned work and replan (then you can remove added work if you please)
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.