Cancel an activity with real work

More
02 Sep 2014 10:42 #1 by mamath
Hi,

I have an issue with cancelled activity. It's possible to cancel an activity even this activity is linked to assignment with real work. I think it's a functional bug, it should be impossible to cancel an activity where somebody have record activity ? do you agree with that ?

The problem is for reporting purpose, the activity is cancelled but with work imputation !

Thanks ...

Please Log in or Create an account to join the conversation.

More
02 Sep 2014 11:10 #2 by babynus
No it is not a bug.
It often happens that you start to work on an activity that is cancelled.
For instance, first work shows impossibility to get expected result, or for work is juste estimation of activity.
Then, you can have real work on cancelled activity.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.026 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.