Hello,
In a project I created activities with type "Phase" and others (sub-activities) with type "Task" to order my stuff.
So I got a phase nammed "Analysis" with some tasks and a phase "Development" with others.
My questions :
1- is it the right way ? What's the impact of activity type on the behavior of the application ?
2- why didn't I get, in my phase, the amount of "validated work" of the sub-activities ?
What's the impact of activity type on the behavior of the application ?
Some fileds may be defined as mandatory depending on type. Also, workflow can be different.
Have a llok at Type fields.
why didn't I get, in my phase, the amount of "validated work" of the sub-activities ?
Because it is designer this wa : in most cases, you don't know the validated work for sub-activities but for main ones, or just for phases.
So your entry should not be erase by null vlues of sub-activities.
An improvement will come in V4.4 to define how you'd like to sum-up validated work .
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.