View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Support us on Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - [SOLVED] left work in activity not updates auto. - ProjeQtOr
 
 

[SOLVED] left work in activity not updates auto.

More
28 Apr 2022 10:59 #1 by chandrashekhar
Hi 
In Activity under Progress tab ->Assignment:  If real work hours are already available & Assigned hours are being added later then left work is not being updated auto!
 

Please Log in or Create an account to join the conversation.

More
28 Apr 2022 12:04 #2 by babynus
Cannot reproduce.

Please describe use case in detail, step by step.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
28 Apr 2022 13:44 #3 by chandrashekhar
Please find the attachment for use case in detail, step by step.
Attachments:

Please Log in or Create an account to join the conversation.

More
28 Apr 2022 14:15 #4 by babynus
Hi,

Behavior is normal : You had 0 assigned, 0 left, and you entered 12 for real. OK
After that, you enter 24 assigned, so it means you add 24 to existing, so left is 24. You'll have to change it manually if it's not whan you expect.
 

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
28 Apr 2022 14:23 #5 by chandrashekhar
Sorry Friend,

But If you add assigned first & then input real, it will work fine for pending as per expected! I can't understand how you are accepting it as Okay?!

Please Log in or Create an account to join the conversation.

More
28 Apr 2022 14:32 #6 by babynus
Because left in not alwayd Assigned - Real.
Imagine you have Assigned = 10, entre Real = 7, left is automatically calculated to 3, but resource can change Left to 5, so reassessed is now 12 (assigned is underestimated)
;) This happens all the time.

Then if you add extra work and set Assigned=15, then left will be set to 10 (you add 5 to assigned, so Left is increased of 5). We don't mind about existing real.
This works the same way is assigned is zero... if you Add some assigned work, left will be added the same added value, whatever existing real work.
Once again, if it's not what you expect (for instance you want to fix some incorrectly assigned work) you can very easily change the left work.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: chandrashekhar

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.039 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.