20 Sep 2018 11:04 #1 by campsy
V7.1.4 : Modify activity (delete,project,..)

Hello,

I have a php timeout after 10 minutes when on activity when i try to delete or change project.

Apache log:
[Thu Sep 20 10:38:02.567549 2018] [:error] [pid 19744] [client 192.168.216.117:51913] PHP Fatal error: Maximum execution time of 600 seconds exceeded in /var/www/projectorria/model/persistence/SqlElement.php on line 2989, referer: project.maxxing.com/view/main.php

Mysql log: no error

sample of action to reproduce:
- I try to delete an activity on main project.
- I try to move an activity from main project to sub project.

server is dedicated , nothing run at this time, maybe the problem is due to wbs update because i don't have this problem on ticket

Here is the structure of the branch

MAIN PROJECT WBS:153 TICKET:1418 ACTIVITE:850
--> CORE WBS:153.1 TICKET:73 ACTIVITE:67
--> PROMOTION WBS:153.2 TICKET:260 ACTIVITE:134
--> CUSTOMER WBS:153.3 TICKET:87 ACTIVITE:49
--> TARGETING WBS:153.4 TICKET:30 ACTIVITE:41
--> MASSCOM WBS:153.5 TICKET:19 ACTIVITE:30
--> MOBILITY WBS:153.137 TICKET:14 ACTIVITE:70
--> DOCUMENT WBS:153.781 TICKET:1 ACTIVITE:1
--> STANDARD DOCUMENTATION WBS:153.782 TICKET:3 ACTIVITE:1
--> OUTILS INTERNES WBS:153.783 TICKET:16 ACTIVITE:22
--> MIGRATION VX WBS:153.784 TICKET:2 ACTIVITE:14
--> FID WBS:153.785 TICKET:0 ACTIVITE:0
--> ENGINE WBS:153.786 TICKET:1 ACTIVITE:4
--> MANAGEMENT WBS:153.787 TICKET:39 ACTIVITE:41
--> CLOUD WBS:153.798 TICKET:1 ACTIVITE:19

I can't reorganize this project , could you help me to solve the problem ?

Thanks

Please Log in or Create an account to join the conversation.

More
21 Sep 2018 09:11 - 21 Sep 2018 09:12 #2 by babynus
Hi,

Can you confirm that if you move a task "inside its project", operation succeeds ?
How long does it take to move an activity from last place to first on sub-project with about 50 activities ?

This is a known bad perfs issue.
We plan to work on subjet on V7.3 (ticket #3543).
As of today, I think only solution is to extend max_execution_time and be patient.

Babynus
Administrator of ProjeQtOr web site
Last edit: 21 Sep 2018 09:12 by babynus.

Please Log in or Create an account to join the conversation.

More
25 Sep 2018 08:46 - 25 Sep 2018 08:47 #3 by campsy
Hi,

Currently these 2 operations are in error, I have used drag and drop on planning.

I will retry when the increase of maximum_execution_time will be done on ProjeQtor server.
Last edit: 25 Sep 2018 08:47 by campsy.

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.038 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.