Change the unit of work/real work allocation

More
24 Oct 2016 16:16 #1 by El Wallos
Hi,

My general settins is set to hours for both parameters (work/real work allocation).

What's happen on my actual data (work on activities and on real work allocation) if I change both parameters to days ? Is it converted to day?

Please Log in or Create an account to join the conversation.

More
24 Oct 2016 16:27 #2 by babynus
Nothing happens to your data.
Data is always stored in days.
When you select to display/input in hours, a conversion is applied.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
25 Oct 2016 13:50 #3 by El Wallos
Thanks for your explication.