[SOLVED] automatical change of project's status

More
20 Nov 2017 11:07 #1 by alay
Hi,

When the last activity is closed, the status's project change automatical with the 'closed' status when we calculate the planning.

Why ? Is there a configuration for that ?

Thanks for you reply

Please Log in or Create an account to join the conversation.

More
21 Nov 2017 09:53 #2 by babynus
It is an automation that will :
- move parent to "in progress" when first activity move into "in progress status"
- move parent to "done" when all activities are "done"

It can be disabled through Menu "Global Parameters", tab "Activity", parameter "auto set parent activity status" in section automation.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
21 Nov 2017 13:53 #3 by alay
Hi,

The value has not been changed and it has "no"

Please Log in or Create an account to join the conversation.

More
28 Feb 2018 09:12 #4 by alay
Hi,

The value has not been changed and it has "no"

mysql> select * from parameter where idUser IS NULL AND idProject IS NULL and parameterCode like '%UpdateActivityStatus%';
+
+
+
+
+
+
| id | idUser | idProject | parameterCode | parameterValue |
+
+
+
+
+
+
| 4582 | NULL | NULL | autoUpdateActivityStatus | NO |
+
+
+
+
+
+

When the last activity is closed, the status's project change automatical with the 'closed' status when we calculate the planning.


Is there another configuration?

Please Log in or Create an account to join the conversation.

More
28 Feb 2018 12:52 #5 by babynus
The configuration in in Global Parameters screen
(never change parameters directly in the Database)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
01 Mar 2018 08:34 #6 by alay
Hi,

We did not change the value directly into database. We have "No" in the BO and "No" in the database. But the project statuses are automatically updated when calculating the schedule or when the last activity is complete

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.051 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.