02 Mar 2018 15:40 #7 by babynus
Please show print screen of Global Parameters.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
05 Mar 2018 17:39 #8 by alay
Attachments:

Please Log in or Create an account to join the conversation.

More
05 Mar 2018 18:04 #9 by babynus
I just tested and behavior is as expected.

Can you try and reproduce use case on demo so that I can have traces to understand what happens ?
(I just set parameter to NO)

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
07 Mar 2018 06:59 #10 by alay
Hi,


I created a new project on demo : #163 - Project 8798-automatical-change-of-project => Statu is "in progress"

I assigned 4 tasks and entered the real times for each resource.
Then I closed the 4 tasks status => tasks status are "closed"

When I go back to the project, the status changed to "done"

I reproduced my problem on demo.
I do not want the status of the project to change according to the number of activities in progress.

Please Log in or Create an account to join the conversation.

More
08 Mar 2018 13:58 #11 by babynus
OK,
So it's not the automation "auto set parent activity status" that is involved.
It is "set to first 'done' status" : with this parameter "On" items automatically moves to status done when there is no left work.

I just set it to no on Demo.
Please try again and confirm that behaviour is the one you expect with this parameter.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

More
14 Mar 2018 07:45 #12 by alay
Hi,

I tested the demo, the problem is resolved but I have an another problem

I thought that the "set to first 'done' status" setting to 'Yes' only changed the activities statuses when I enter the real work. And not the parent elements (activities, projects), since the parameter "auto set parent activity status" is setting to 'No'.

As I understand it, if I do not want projects to change status I have to specify the following parameters:
- "set to first 'done' status' to 'No'
- "auto set parent activity status" to "No"

But if I want the status of an activity to be "done" when the rest to do is at zero how should I do?

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.049 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.