OK,
So it's not the automation "auto set parent activity status" that is involved.
It is "set to first 'done' status" : with this parameter "On" items automatically moves to status done when there is no left work.
I just set it to no on Demo.
Please try again and confirm that behaviour is the one you expect with this parameter.
I tested the demo, the problem is resolved but I have an another problem
I thought that the "set to first 'done' status" setting to 'Yes' only changed the activities statuses when I enter the real work. And not the parent elements (activities, projects), since the parameter "auto set parent activity status" is setting to 'No'.
As I understand it, if I do not want projects to change status I have to specify the following parameters:
- "set to first 'done' status' to 'No'
- "auto set parent activity status" to "No"
But if I want the status of an activity to be "done" when the rest to do is at zero how should I do?
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.