I have a problem with meetings. When I assign a resource to a meeting and compute an updated planning, I often get the message "Following tasks could not be completely planned" and I see that the resource doen't have enough free time for the meeting.
Indeed, there is planned work on another activity.
I thought meetings took precedence over other activities so I don't understand why the other activity is not rescheduled later.
The conflicting activity (planning mode is ASAP) is in the same project but not the same subproject.
When rescheduling, I tried to select the root project + all the subprojects + all the other projects where the resource is involved with no luck.
I tried to lower the priority of the conflicting activity but then the planned time goes to another activity, not the meeting.
What version of ProjeQtOr are you using ?
We fixed an issue on V6.5.6 (#3241) leading to incomplete planning of meeting depending on start time and work.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.