Hi,
I have a problem with the automatic calculation of the rate of progress.
in my schedule I have:
1.a project
2.two project activities
3.resources
by making the allocation of resources to the activity and by assigning the working days the progress is not done automatically on the rate of progress of the project.
see attached image of my schedule
Progress on activities is not calculated from progress on Project, this has no sense : how do you determine progress of a project, moreover of a big project.
Process is revese : you define assigned work on activities, then resource enter real work on Timesheet. This will calculate progress on activiities, and will be consolidated on parents up to top project.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.