I have some resources working in part-time : they have each wednesday afternoon for themself.
I read some posts and find the way to define resource in part-time using calendar, but it seems to be only for 1 day off. In my case, the resources are 1/2 day off each week.
Is it possible to define calendar (or other method) with only 1/2 day off each week ?
Unfortunately ProjeQTOr does not manage part-time from calendars.
To record Wednesday afternoons of these resources as not worked, you will need to record
absences
.
choose half day in duration and indicate Wednesdays as recurrence or enter a period between two dates.
Upon validation, all Wednesdays from the current date or between the two dates will be marked with a half day of absence
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.