ProjeQtOr free project management software - real work allocation - ProjeQtOr
 
 

real work allocation

More
09 Nov 2016 17:51 #1 by julius.kimani55
my real work allocation time sheet is inactive. i expected them to be active so as i can fill number of days worked. please help
also do the fields take 0 or 1 only?
The topic has been locked.
More
10 Nov 2016 09:41 #2 by protion
Replied by protion on topic real work allocation
Hello
I do not understand your request.
Your problem and you are unable to fill out the time allocation sheet, whether the problem may be the status of your activities.
cordially
Bonjour
Je ne comprends pas très bien votre demande.
Votre problème et qu'il vous est impossible de remplir la feuille d'imputation des temps, si oui le problème peut venir du statut de vos activités.
cordialement
The topic has been locked.
Moderators: babynusprotion
Time to create page: 0.039 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.