Hello,
We have a question about the management of ProjeQtOr.
But first, we have to explain how we use the application.
When we create a project and an activity in ProjeQtOr, we assign it to a team using the field « responsable » and the part « assignation » and we indicate the workload.
When all the necessary fields are completed, we go to the planning view and calculate the planning.
Thanks to this action, the activity appears in the reporting of the team.
Each team is made up of different people. When the team leader wants to assign someone of his team to an activity, he changes the field « responsable », putting the name of the person concerned and taking of the team and do the same thing for the part « assignation ».
Then, he doesn’t calculate the planning again.
We have a problem because each information is distorted in the report of the teams. When the team leader looks at the activities of each person of his team in the report, there are some mistakes and the workload of the person doesn’t appear if he/she didn’t make his/her imputation.
My question is to know :
- If we are using the application correctly ;
- If ProjeQtOr allows us to manage named assignment when the assignment starts from a team.
I hope everything is clear, it isn’t easy to explain. Don’t hesitate if you have any question.
Thank you in advance.