I have created a team which include 4 team member. Name : Team1
I have Allocate this team to a project
I’m creating an activity for this project, i’m assigning the Team : Team1 to this activity.
So far everything is ok, all 4 members can see theire activity.
The issue is in the TimeSheet, in their TimeSheet, they see all the activities but the project related to those activities, does not appear even if the team is assigned to the projet.
The only way for the team member to see the project in TimeSheet is to allocate the ressource in the project.
Is it normal that i have to assign the ressource even if he his a part of the team that is already assigned to the project ?
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.