18 Jul 2019 18:22 - 18 Jul 2019 18:25 #1 by fmartin
Hi,

I would like to create some activities in advance, beginning 2020/01/01, ending 2020/12/31.

I would like to know if that's possible to hide that activity from work input tab as the beginning date hasn't been reached yet.

I've been trying multiple things, but I can keep on seeing it in the input tab and I can input working time on it without any warning whatsoever.

Some help would be really appreciated ;)


Best regards
Last edit: 18 Jul 2019 18:25 by fmartin.
The topic has been locked.
More
25 Jul 2019 09:38 #2 by babynus
It is possible if you check "hide not handled items". Then if you let the activity it a status that is not handled, it won't be displayed on Timesheet.
Ohter solution, is to check "under construction" on project. Then all activities of the project will be hidden on Timesheet

Babynus
Administrator of ProjeQtOr web site
The topic has been locked.
Moderators: babynusprotion
Time to create page: 0.041 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.