Dear team Projeqtor,
Thanks for this application, really important for us now since 4 years of current use
We encountered a new problem with planification
I will exposed task details that have problem
In the present case, a task without dependency, of type "activity", of a project of priority 290 is scheduled before a task without dependence, of type "activity", of a project of priority 100.
NB: the resource is unique and identical for the 2 tasks,
NB: the remaining charge is identical for the 2 tasks.
NB: the planning mode is at the earliest for the 2 tasks
Task : AQVIEW_2200_ANO_06: Document RAPSTAT_ICH inaccessible (#3436)
Project priority : 290
Ressource assigment on project "project manager" : 100% all date
Project type : internal
Task status : not started (assigned)
Task Type : Activity / task
Load : 1d
assigment of task : HER
Planned Start date : 07/05/2020
Planned End Date : 08/05/2020
Task Priority : 500
WBS : 1.5.7.1
Task : Exécution protocoles de validation QI PREPROD (#3787)
Project priority : 100
Project type : internal
Ressource assigment on project "project manager" : 100% all date
Task status : not started (assigned)
Task Type : Activity / task
Load : 0,25d
assigment of task : HER
Planned Start date : 24/07/2020
Planned End Date : 24/07/2020
Task Priority : 500
WBS : 2.5.5.2.1
Plan task is runned each day by cron or by admin without any change
One of our developers is going to be working on this case next week, because it has a big impact for us, but we would be very interested in a solution that you could identify
Thanks for help