Task date

More
14 Jui 2019 12:16 #1 by lsigroup
Task date was created by lsigroup
Hi,

On the underligned task, my ressource has to work today on that. I force validated end date to today, bu even when launching new calcultaion, green bar still blocked on yesterday.

Please advise.
Attachments:

Please Connexion or Create an account to join the conversation.

More
18 Jui 2019 09:40 #2 by jmmbb
Replied by jmmbb on topic Task date
Hello,

does your ressource have free work time for yesterday ?
If timesheet isn't full, Projeqtor assume that ressource can have done work yesterday but no update real work...

Regards,

Please Connexion or Create an account to join the conversation.