ProjeQtOr free project management software - No way to filter works' global view by closed date - ProjeQtOr
 

No way to filter works' global view by closed date

More
06 Nov 2019 10:21 #1 by pakkes
Hi,
yesterday I closed several activities.


Then, today I've tried to add a simple filter to get all activities closed on a certain date. But the filter doesn't produce results.


Is there something I do wrong or maybe a different procedure I need to follow?
Many thanks in advance.

Regards
Attachments:

Please Connexion or Create an account to join the conversation.

More
08 Nov 2019 09:40 #2 by babynus
I checked and it works ffne.

1) check that your activities have correct closed date

2) if you closed also parent project, take care that this defined some "archiving" mode.
When a project is closed, it is considered as "archived" and so you won't see closed activities for this project.
Only way to see them, is to enter the "archive mode", that you can activite through the Project Selector parameter button.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: pakkes

Please Connexion or Create an account to join the conversation.

More
08 Nov 2019 10:09 #3 by pakkes
Many thanks for your reply and suggestions. I will follow your suggestions, probably I did a mistake.
Regards

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion