10 Jan 2020 16:26 #1 by christophebolmontcharpy
I've got a project since 01/01/2020 Ok ?
i make activities this week but automatiquely projeqtor make a date at 19/10/2017 !!! and ré eval my work 1 hour at 2 hours !

When i go to imputation (allocation in english ?) i go to 19/10/2017 but i never saw reel work projeqtor take for me ...

it's a joke ? i lost my time since 2 days with this problème



I've you got ideas ?

Thanks

Sorry for my bad english
Attachments:

Please Connexion or Create an account to join the conversation.

More
10 Jan 2020 16:40 #2 by babynus
Replied by babynus on topic Help !
Sorry, I don't understand your issue.

Can you give details steps by steps.
1) whet you do
2) what you get
3) what you expected to get

Also please indicate which version of projeqtor you are using, and of you get any error in log file.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion