11 Mai 2020 16:35 #1 by mercyril
Hello

It is possible to define a new calendar with half day in it ?

I have a ressource guy that works 1.5J by week
I want to associate a calendar where three morning will be workings 'days'.

It is possible ?

Perhaps in a next release ?

Regards
Cyrille

Please Connexion or Create an account to join the conversation.

More
11 Mai 2020 16:40 #2 by babynus
Replied by babynus on topic calendar with half day
No it is not possible.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
11 Mai 2020 17:10 #3 by mercyril
Replied by mercyril on topic calendar with half day
It is possible to do that by another way ?

Please Connexion or Create an account to join the conversation.

More
11 Mai 2020 17:11 #4 by mercyril
Replied by mercyril on topic calendar with half day
not the calendar, but manage 3 morning by week for a ressource ?

Please Connexion or Create an account to join the conversation.

More
12 Mai 2020 14:24 #5 by alainforma
Replied by alainforma on topic calendar with half day
Hi,

Half day is not automatically possible, to get that, you have to go to "absences" screen and fill thoses days with 0,5 for the resource
The following user(s) said Thank You: mercyril

Please Connexion or Create an account to join the conversation.

More
12 Mai 2020 15:03 #6 by mercyril
Replied by mercyril on topic calendar with half day
Hi

I had seen by this way, and you confirm.
Thank you.

BR
Cyrille

Please Connexion or Create an account to join the conversation.