View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - [SOLVED] Milestones progress - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

[SOLVED] Milestones progress

More
08 Jui 2015 11:31 #1 by anisdz2015
Hello,
I noticed that the percentage of milestones is always either 0% or 100%!
is that there's way of having a percentage of 25%, 50%, 33%
thank you

Please Connexion or Create an account to join the conversation.

More
08 Jui 2015 13:02 #2 by babynus
Replied by babynus on topic Milestones progress
Yes,
a milestone have no work, so it is just "no reached" or "reached".
There is no prgress on milestone.
The progress must be read on activities preceding (or generating) the milestone.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: anisdz2015

Please Connexion or Create an account to join the conversation.

More
08 Jui 2015 14:34 #3 by anisdz2015
Replied by anisdz2015 on topic Milestones progress
Thank you Babynus
is that there's way of having a percentage of 25%, 50%, 33% in activities progress ?

Please Connexion or Create an account to join the conversation.

More
08 Jui 2015 14:47 #4 by babynus
Replied by babynus on topic Milestones progress
Of course : progress is [real work] / ( [real work] +
)
So it can take any value beetwen 0% and 100%

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: anisdz2015

Please Connexion or Create an account to join the conversation.

More
08 Jui 2015 15:30 #5 by anisdz2015
Replied by anisdz2015 on topic Milestones progress
Its not working for me
I introduced two dates with a fixed duration planning, status in progress,
but progress still does not change 0%.
Can you please help me to set it or can you send me an example ?
Thanks

Please Connexion or Create an account to join the conversation.

More
08 Jui 2015 15:41 #6 by babynus
Replied by babynus on topic Milestones progress
Go to demo.projeqtor.org
Connect as manager/manager
View activities 501 or 477

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.040 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.