ProjeQtOr free project management software - How to specify "for the duration of this activity"? - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

2 décembre 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

10 et 11 décembre 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

16 et 17 décembre 2025 (9h-12h30)

 

 

 

How to specify "for the duration of this activity"?

More
21 Jui 2017 13:40 #1 by NarayanAras
I have an activity, which has two resources assigned to it. The main effort comes from the first resource.

The second resource is support-provider, and he is lightly engaged with that activity as long as it runs. (say, at the rate of 1 hour per day).
(This is a typical scene with a consultant.)

But how to specify this in the Assignment?

The work-around seems to be very long-winded:
  1. Estimate the total effort (in hours) required by Resource#1, and enter it in against the task.
  2. Convert this number with the working hours/day to find how many working days are needed.
  3. Calculate how many of consulting hours are needed for this activity, at the rate of 1 hour per day.

So, if the activity is going to last for 10 days, we allocate 10 hours to resource#2 (calculated at the rate of 1 hour per day).

What happens when the task requires more time to complete:

Suppose resource #1 reports a few hours of left work and asks for extension of the activity,
ProjeQtor will not automatically extend the assignment of Resource #2 to the activity.
We have to manually adjust the remaining work for him.

How to avoid that, and make it fully automatic?

Please Connexion or Create an account to join the conversation.

More
22 Jui 2017 18:52 #2 by babynus

But how to specify this in the Assignment?

Set assignment rate at 10% (or less depending on expected result)

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
23 Jui 2017 11:23 #3 by NarayanAras
No, perhaps my question was not clear.

We have already assigned the second resource at (say) 10%. But because we specify the effort hours for each user, his effort reaches 100% (no left work) when the original deadline for the task is reached.

But the first resource could not finish his work, so he wants extension.

During this extended period, resource 2 is not prompted to work, because his contribution is over (total x hours, at 10% FTE).

This is why we need to specify that the 2nd resource must go on working till the end of the task, at the same % of FTE.

Please Connexion or Create an account to join the conversation.

More
23 Jui 2017 13:59 #4 by babynus
There is not planning mode such as "x days as long as needed".
ProjeQtOr is work driven, this means you must define the total work for the task, this will define duration, not the other way round.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
27 Jui 2017 07:28 #5 by NarayanAras
I do understand that, but when the task is split among multiple resources, any delay/extension of the task would require re-planning for all those resources.

Any one of the resource can request extension of the task at any time (by entering some left work). But the software does not warn the others about this proposed extension. Of course some of the resources may not have to extend their work on this task, but some may have to stay till the very end of the task. So they will have to match the duration.

In fact, there is one more use case: Some of the resources may not be available if the task is delayed/extended; or their original allocation to this project may be expiring.

All these use cases are not handled in ProjeQtor.

Please Connexion or Create an account to join the conversation.

More
28 Jui 2017 00:28 #6 by babynus

All these use cases are not handled in ProjeQtor.

No.
And I'm affraid ProjeQtOr does not make coffe either.
A tool will help but will never replace communication

NB : maybe I would prefer to spend some time to have ProjeQtOr able to make coffe and bring ot to me than trying to cover every use case.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.035 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.