ProjeQtOr free project management software - How to modifiy dates of a task - ProjeQtOr
 
 

How to modifiy dates of a task

More
26 Mar 2015 14:32 #1 by Sterwen
Hi,

I am learning how Projeqtor works. I have search within the forum without results. So, I hope not asking an already treated subject.

I have created a project and then, an activity. The first dates fr the activity were may 5th. However, the meeting has been postpone on may 7th.
Although I modified the dates in the activity control panel, the activity remain scheduled on may 5 in the Gantt.

I don't find how to modify easily without deleting the activity and creating a new one.

Could someone help ?

Thanks in advance.
Sterwen

"Le progrès ne vaut que quand il est partagé par tous" : merci à ceux qui partagent !
The topic has been locked.
More
26 Mar 2015 14:51 #2 by babynus
hi,

ProjeQtOr runs effort driven planning, based on Work.
Default planning mode is "as soon as possible" .
If you need fix date, use corresponding planning mode.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: Sterwen
The topic has been locked.
Moderators: babynusprotion
Time to create page: 0.025 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.