Overrun highlight

More
18 Nov 2014 18:36 #1 by hle
Overrun highlight was created by hle
Hi,

I used projectOR for several years for tracking bugs or following work allocation but never tried to use the planification module up to now.

I was surprised by several aspects - may be I totally missed the point... :
  • Is there any way to visually distinguish between Activities on track and Activities on overrun (whatever the overrun origin : remaining work reevaluation or real work allocation exceeding the anticipated effort ? Everything stay green :dry: ... on the Gantt diagram.
  • when a developer updates a remaining work, he or she can silently impact the whole planning. Is there a way for the project planner to be notified of the shift ? And its origin ?
  • Is there any validation possible to prevent remaining work changes without notice ? Including a what-will-happen developer curious about the impact of tuning this "weird" field just to see its effect.. :whistle: .

Thanks in advance
The topic has been locked.
More
18 Nov 2014 19:47 #2 by babynus
Replied by babynus on topic Overrun highlight

Is there any way to visually distinguish between Activities on track and Activities on overrun (whatever the overrun origin : remaining work reevaluation or real work allocation exceeding the anticipated effort ? Everything stay green :dry: ... on the Gantt diagram.

On Gantt Diagram, you have mostly view over planning dates. Tasks become red when planned end date is over validated end date.
To have overview about work overrun, just have a look at report Work / Work synthesis per activity.


when a developer updates a remaining work, he or she can silently impact the whole planning. Is there a way for the project planner to be notified of the shift ? And its origin ?

Yes, alerts can be send when planned work (real+left) is over validated or over planned work.
Have a look at indicators.

Is there any validation possible to prevent remaining work changes without notice ? Including a what-will-happen developer curious about the impact of tuning this "weird" field just to see its effect.. :whistle: .

You can define alerts (as described above) of have a validation process of real work allocation.
There is possibility to submit and validate weekly real work, so that project leader has an overview about global work on project.

Babynus
Administrator of ProjeQtOr web site
The topic has been locked.
More
19 Nov 2014 11:36 - 19 Nov 2014 11:40 #3 by hle
Replied by hle on topic Overrun highlight
Thank you for all those replies.

babynus wrote:

Is there any way to visually distinguish between Activities on track and Activities on overrun (whatever the overrun origin : remaining work reevaluation or real work allocation exceeding the anticipated effort ? Everything stay green :dry: ... on the Gantt diagram.

On Gantt Diagram, you have mostly view over planning dates. Tasks become red when planned end date is over validated end date.


Is a four stage approach possible :
  1. activity definition (and dependencies)
  2. resource allocation (effort)
  3. using the gantt views, computation of the planning
  4. validated start and end dates automatic setting ? i.e. setting validated dates = planned dates globally, without manually entering each date for each activity ?

babynus wrote:

There is possibility to submit and validate weekly real work, so that project leader has an overview about global work on
project.


When entering real work allocation, I wonder about the differences between submit work and validate work buttons and how they affect planning computation ? No impact for instance until the project manager has validated his/her team work allocation entries ?

THX :-)
Last edit: 19 Nov 2014 11:40 by hle.
The topic has been locked.
More
19 Nov 2014 17:09 #4 by babynus
Replied by babynus on topic Overrun highlight

Is a four stage approach possible :
activity definition (and dependencies)
resource allocation (effort)
using the gantt views, computation of the planning
validated start and end dates automatic setting ? i.e. setting validated dates = planned dates globally, without manually entering each date for each activity ?

Yes, this is exactly in ProjeQtOr scope.
NB : definition of dependencies can be eased in Gantt view (drag & drop mode)
NB : to save validated dates, use correspondng button in plannong screen (the one woth the check, beside print button)


When entering real work allocation, I wonder about the differences between submit work and validate work buttons and how they affect planning computation ? No impact for instance until the project manager has validated his/her team work allocation entries ?

Submit button appears only if connected user is the current resource. It is for the resource to submit the weekly work.
The validate button apperas only for project leader (or other profile habilitate to...) to validate the submitted work.
Both have no effect on planning calculation : it only locks real work for the corresponding week.

Babynus
Administrator of ProjeQtOr web site
The topic has been locked.
More
19 Nov 2014 18:17 #5 by hle
Replied by hle on topic Overrun highlight
Thanks a lot for your assistance, from St Martin du Touch :-) We seem to be neighbours.
French not allowed in the forum :silly: ?
The topic has been locked.
More
19 Nov 2014 18:55 #6 by babynus
Replied by babynus on topic Overrun highlight
Hi neighbours,

Fly Aircrafts at St Matin ? :whistle:

English is mandatory in the forum so that most community users can benefit of questions and answers :)
Frensh is available only through professionnal support service :whistle:

Babynus
Administrator of ProjeQtOr web site
The topic has been locked.
Moderators: babynusprotion
Time to create page: 0.039 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.