Automatic Calculation Option of planning: it would be interesting to have this option you can enable or disable for the calculation of the schedule is automatic after the change of use, ramainning work ....
Well, autimatic calculation on each update (real work input, left work, ...) is possibly not an option for several main reasons :
- it would be much time consuming, leading to bad response time on each of the concerned operations (and they are many) and could lead to conflitual access (and possibly to dead locks)
- calculation of planning should always be a Project Leader decision.
- each time planning is calculated, Project Leader must decide scope of planning : single project, groupe of projets, all projects : auitomatically recalculating planning for single project without this Management decision could lead to unexpected results
But an option to recalculate planning on each change on planning view could be studied (I had a try almost ready for V5.0, but possibly it could be finalized for V5.1).
Add a view with the possibility of updating the remainning work,,,, for details of work planned
This already exists in the Real Work allocation screen. Isn't it what you expect ?
Ability to change the remaining work directly in the assignments table , aren't being forced to open assignment by assignment
Request recorded as Ticket #1776
Add Filter "resource" in the views Planning and scheduling by resource (why not also a "Team" filter)
Resource planning already exists, but is a different view.
Add View milestones (with Planning representation )
This looks like "ProjectPortfolio, where you can choose to display milestones
add to the reporting an occupancy rate / rate of inactivity of resources (in workload)
There are already several reports of this kind.
I don't really understand what you expect.
it would be interesting to add the "Origine" field in actions , problems , Risk , that can be set in a valeures list (such as the"action type")
Request recorded as Ticket #1777
add a reporting with the list of milestones (Getting prod, delivery, ...) ==> so can be attach it in today screen
Could you detail how you would expect this list ? (there are already list of todo items, which include milestones)