ProjeQtOr free project management software - Version 4.5.4: problem with planning - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

21 août 2025 (16h-17h30)

4 septembre 2025 (16h-17h30)

16 septembre 2025 (10h30-12h)

 
 

Planifiez avec ProjeQtOr

17 et 18 septembre 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

24 et 25 septembre 2025 (9h-12h30)

 

 

 

Version 4.5.4: problem with planning

More
23 Jan 2015 15:14 #1 by igio80
Hi guys.
I downloaded version 4.5.4 and I'm using for the first time this software.
Probably something wrong because I can not get automatically update the planning (Gantt) when I finish a task before the scheduled date.
In practice, if the first task is scheduled between January 1 to 10 and the second connected (Successor Element) from 11 January, when I finish (closed) the first task on January 5, I expect that the second task automatically starts from 6 and instead continues from the day 11 ... why? I assigned the task to a resource and set the dates requested. Thank You.

Please Connexion or Create an account to join the conversation.

More
23 Jan 2015 19:39 #2 by babynus
Did you update left work on first task so that there is no left work ?
Can you create an example on demo ?

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
26 Jan 2015 09:46 #3 by igio80
Resolved! I must update left work. Thank you very much.

Please Connexion or Create an account to join the conversation.

More
08 Mai 2015 11:21 #4 by igio80
How can I edit planned in my activity? It's disable for editing.

Please Connexion or Create an account to join the conversation.

More
08 Mai 2015 11:47 #5 by babynus
You cannot.
Planned is calculated : planned = real + left.

RTFM

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: igio80

Please Connexion or Create an account to join the conversation.

More
08 Mai 2015 13:12 #6 by babynus
For information, due to possible common confusion, in V5, "Planned work" will be renamed "Reassessed work"

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.076 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.