Each resource can have a personal calendar
It will be usefull to have their own work hours (every resource don't work 7 or 8 hours per day and don't have same start and end time)
Work hours do not interfer with resource planning.
Work hours are only taken into account for :
- convertion from hours to days (and must be fixed for all resources)
- calculation of indicators in worked hours (and must be fixed for all projects)
But how does it manage conversion from hours to days for all resources ?
When you display work for all project in days, how is done conversion from hours to days for all resources ?
I guess there is, like in MS-Project, some global definition of convertion.
So hours on resource calendar will only define working period.
You can get the same changing the capacity of the resource.
For instance, define work period of 8 hours a day.
Resource working 7 hours a day have capacity of 0,75.
Resource working 9 hours a day have capacity of 1,25, and a specific calendar with only 4 working days per week.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.