I'm doing this as user that has admin privileges on all projects.
I'll keep in mind the access rights, because it's strange that there are no error messages issued.
thanks for the remarks, I've found where was the problem, or at least part of it.
I have created "internal" projects for each of my clients so I can easily edit my invoices for each of them at the end of the month.
Then I have "time & materials" subprojects of these "internal" projects and I create activities inside these subprojects.
Until now I was declaring rates of affectation of resources only for the subprojects, while they were at 0% for my "internal" parent projects. Until now this was working fine, but for the last upgrade the calculation of planned work was providing a null result. Just giving a proper rate to affectation for the parent projects has solved the problem. Now planned work seems to be correctly calculated again.
Any suggestion to better understand such behaviour is welcome.
Ciao
Jean Pierre
Last edit: 08 Jan 2015 18:36 by jphuart. Reason: simplify explanation
You put the finger on the correct origin of the issue.
In V4.5, the affectation rate determination has changed because it now takes into account start and end dates of affectations.
The fact is that % rate is a limitation that is controlled on sub-project and top-projects.
So, the applied affectation rate limit on each sub-project cannot be more that rate on top project.
So, having rate of 0% should have brought the issue on previous versions, but this was possibly a bug that new functionality fixed.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.