Using v10.2.3, I notice we can get different results from two Planning reports which should give the same result.
I think the issue occurs only for months having both real and planned work.
Example for the current month (April) :
- monthly planning resource/project :
- total for resource "YP" = 19 d
- total on project = 706.06 d
- yearly planning resource/project (only looking at the month of April) :
- total for resource "YP" = 38.8 d
- total on project = 1124.77 d
Monthly view is a detail day by day.
So if on that dat there is real work, this value is taken in account, otherwise planned work is taken into account.
Yearly view is a global view, where same detail cannot be applied.
So displayed value = Real + Planned.
So if you did not recelculate the planning, this view is wrong, is duplicated some data where real work was entered differently from planned work.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.