i notice this on V11.1.4 and even on DEMO.
When you set cost for activity on project (see project test on DEMO), the total cost is set to project (normal).
If you set cost for activity to another value, it is well computed (is : changing cost of activity #8 to 10 change the relkated cost of project.
But, if you set cost to 0, project's cost is not updated...
Normal if it is the only activity on the project.
If Project has activities with costs, then project costs is calculated from activities.
If not, Project costs can be manually changed, so value not erase. This leads to fact that last value on last activity is preserved on project
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.