good day projeqtors'
I would appreciate having the possibility to first automatically plan an activity, fix it's auto-generated planning and then switch to manual planning to edit the proposal ?
Is there anyway to do that ?
thanks in advance,
Thanks for your answer, is there anyway that this feature gets onto your backlog list of improvements ? I mean the automatic planning is a great functionality for long terme capacity planning but gets heavy to manage for shorter term.
Cheers,
No, as that's not the way ProjeQtOr works : it is not a way to "draw" a gantt, but a powerfull calculation tool to show you when your projets end with the capacity of your resources.
You may use the new "Duration driven" planning mode, but this won't calculate first. You always indicate what you want.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.