I have :
- a ressource affected at 50% on a projet,
- an unique activity in th eproject (with the ressource at 100% and a effort of 2 days)
when I launch the planing calculation with : the activity is planned on 2 days and not 4 ==> It seems that affectation is not taken into account in planing calculation.
(I use version 5.0.3)
Affectation rate is taken into account... on a weekly basis.
It is considered that if a resource is affected 50% on P1 and 50% on P2, it should not work half days on each, but half weeks on each.
It means planning will set 2,5 days on P1 then 2,5 daus on P2.
Try and change your effort to 5, you'll see what I mean.
If you want a daily basis restriction, use assignement rate at 50%.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Cookies settings
×
Functional Cookies
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Please login to see yours activities!
Other cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.