07 Oct 2015 20:44 #1 by bsimon
I have :
- a ressource affected at 50% on a projet,
- an unique activity in th eproject (with the ressource at 100% and a effort of 2 days)
when I launch the planing calculation with : the activity is planned on 2 days and not 4 ==> It seems that affectation is not taken into account in planing calculation.
(I use version 5.0.3)

Please Log in or Create an account to join the conversation.

More
09 Oct 2015 09:10 #2 by babynus
Affectation rate is taken into account... on a weekly basis.
It is considered that if a resource is affected 50% on P1 and 50% on P2, it should not work half days on each, but half weeks on each.
It means planning will set 2,5 days on P1 then 2,5 daus on P2.
Try and change your effort to 5, you'll see what I mean.

If you want a daily basis restriction, use assignement rate at 50%.

Babynus
Administrator of ProjeQtOr web site

Please Log in or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.035 seconds

Cookies settings

×

Functional Cookies

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Please login to see yours activities!

Other cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.