[SOLVED] Planner calculation (last version)

More
04 Déc 2019 15:29 #7 by QUANTAMEDICAL
You will show detailled information
First screenshoot : task must be planned just after predecessor end


Second screenshot : task planned between predecessor and task of first screenshot


Third screenshoot : task are from different project, then this screenshoot show project priority


Planning are calculated by admin, on all project.
Even each morning by automated task


Thanks for your help
Attachments:

Please Connexion or Create an account to join the conversation.

More
04 Déc 2019 15:42 #8 by QUANTAMEDICAL
Screenshot of planning in 2 parts



User allocation on 2 projects



Thanks again
Attachments:

Please Connexion or Create an account to join the conversation.

More
05 Déc 2019 10:46 #9 by alainforma
Hello,

Please could you :
- highlight the lines to be read on Gant.
- SHow the resource allocations on projects and assignations on activities for each involved
- What about and where is the predecessor ? Do not really understand...
- Check the cell " show wbs " on Gantt view.
It will make it easy for me to understand the whole links.
Regards.

Please Connexion or Create an account to join the conversation.

More
19 Déc 2019 17:01 #10 by QUANTAMEDICAL
Problem has been corrected for an undefined reason
We will open a new question if incident reproduced


Thanks