10 Mar 2021 04:13 - 10 Mar 2021 04:14 #1 by rainbow
Hi,

I changed the global parameters/activity/planning - "show resource in Gantt" setting to 'name', but the display of resoruces in Gantt table column and chart area still remain as resources initials instead of resources names. I also tried to clear cache but still no changes. Would you advise how to enable or any other settings required? I included screenshots as attached.

Thanks,
Rainbow
Attachments:
Last edit: 10 Mar 2021 04:14 by rainbow.

Please Connexion or Create an account to join the conversation.

More
10 Mar 2021 08:59 #2 by mkavurcic
Try - User parameters -> Display ->Graphic Interface behaviour -> show resource in Gantt
The following user(s) said Thank You: Gautier, rainbow

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.031 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.