View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - [SOLVED] Planning four task of 0,25 day in one day - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

[SOLVED] Planning four task of 0,25 day in one day

More
03 Sep 2021 18:35 #1 by nhedhili
Hello 
we need to plan four tasks each of 0,25 day for one ressource l in one day.
assignation of the ressource  is 0,25 for each task with 100%
planning mode is regular between two dates 
ressource capacity = 1 
We tried all the combinations only three tasks can be planned , I tried one task of 0,5 day and two tasks of 0,25 day assignation it only can schedule 0,75 day of assignation whatever the combination.

Thanks  for your help and assistance 

Please Connexion or Create an account to join the conversation.

More
07 Sep 2021 11:19 #2 by Flou
Hello,

What is the rate of your resource affection on your project ? 
Is it possible that your resource is assigned in parallel to another activity of another project?

Please Connexion or Create an account to join the conversation.

More
07 Sep 2021 15:39 #3 by nhedhili
Hello
the rate is 100% and the ressource is not assigned to other tasks or porjects.
if I affect them to two tasks 0f 0,5 day it works fine , but if I affect them same period in four tasksof 0.25 day it ony takes into consideration onl three tasks of 0.25 day in the same day which is a strange behaviour

Please Connexion or Create an account to join the conversation.

More
09 Sep 2021 09:21 #4 by babynus
Hi,

I could not reproduce.?
Tested on Demo, you can have a look to project ProjeqtorTest01, with brand new resource ProjeqtorTest01.
Works really as expected.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
10 Sep 2021 19:43 #5 by nhedhili
issue is solved , there was a task in another project not included in the calculation , doing calculculation fior all the prject soved fixed the planning.
thank you for your assistance

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.054 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.