View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Project recalculate - Page 2 - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Project recalculate

More
30 Jan 2012 16:16 #7 by ekolossov
Replied by ekolossov on topic RE : Project recalculate
Looking like the fix you provided not working - when work hours assigned to developer it will extend the bar to the beginning of the project for some reason and will calculate the planned hours based on that

Regards,
Evgueni

Please Connexion or Create an account to join the conversation.

More
30 Jan 2012 17:16 #8 by babynus
Replied by babynus on topic RE : Project recalculate
Hi,
I don't understand.
The prevoius issue was about work calculation, and you're now talking about gantt chart.
Could you please explain ?

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
30 Jan 2012 17:41 #9 by ekolossov
Replied by ekolossov on topic RE : Project recalculate
I am talking about system response on click button "Calculate activities planning" - this is when system been recalculating work

Please Connexion or Create an account to join the conversation.

More
30 Jan 2012 18:33 #10 by babynus
Replied by babynus on topic RE : Project recalculate
Hi,
I realy don't understand.
There is no issue on the planning.
The issue was about real work update when modifying assignment.

The fix fixes this.
But does not correct data.
Can you test :
- find one assingmnt with the error
- go to the "real work input" for resource assigned, and save
- check the assignment : it must be corrected.
- then update again assignement : the real work sould not increase any more with the fix

If you still have an issue, please describe your step by step case (described like above)

Thanks.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.029 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.