View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - [SOLVED] Adding public holidays in standard calendar doesn't work - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

[SOLVED] Adding public holidays in standard calendar doesn't work

More
09 Mar 2023 12:29 #1 by kbcgwi
Hi,

Since the beginning of the year, we can't add the public holidays in the standard calendar. We did it each year before, and we never have any problem.
When we click on the button, it don't show any error, but the days are not set as public holidays. And in the "imputation" view, the related days are not greyed out.

I just try after update to the newer version (V10.2.3), but the result is the same.

It is a bit problematic for us because these public days off are not taken in account for the planning calculation.

Please Connexion or Create an account to join the conversation.

More
09 Mar 2023 18:13 #2 by babynus
Cannot reproduce.
All works fine on my instances.
Do you have any error in log file ?

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
10 Mar 2023 08:50 #3 by kbcgwi
Please find attached the log file while trying to add public holidays in calendar (in Script log level), but no error are shown.
Attachments:

Please Connexion or Create an account to join the conversation.

More
10 Mar 2023 09:17 #4 by babynus
Hi,
No error in log (NB : script log level not necessary, we look for errors)
Can you explain how you add the holidays ? Some screenshots ?

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
10 Mar 2023 09:27 #5 by kbcgwi
I set the script log level because with the other levels, I don't see anything in the log file.
Attached is a screenshot of the calendar view, but I don't think that you will see something wrong (I click on "Add these public holidays to calendar", but only the weekend days are marked as days off).
Also, when I click on a specific day on the calendar on the bottom, nothing happen too, the day is not marked as a day off.
I try to create a new standard calendar, but the result is the same.
Attachments:

Please Connexion or Create an account to join the conversation.

More
10 Mar 2023 16:30 #6 by babynus
Strange, no issue , no erreur.
Do you connect as admin to manage the calendar ?

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.043 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.