Exactly : assignment is not created for "fix duration" (and "Constrained duration" and "Duration driven") because this planning mode does not expect to have work.I find the issue : for planning mode "fixed duration", there is no auto assignment, so status can't change !
Is it possible that, for fixed duration, status can be change even if there is no assignment ? I understand that there is no assignment because there is no work element for fixed duration and manual advancement set, but it leads to no intuitive behaviour for users.
Please Connexion or Create an account to join the conversation.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.