View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Status "in progress" does not change real start date - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

6 mars 2025 (10h30-12h)

3 avril 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

18 et 19 mars 2025 (9h-12h30)

15 et 16 avril 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

18 et 19 février (9h-12h30)

25 et 26 mars (9h-12h30)

 

 

 

Status "in progress" does not change real start date

More
08 Jan 2025 16:57 #1 by jmmbb
Hello,

i facing a strange issue.
since today (no change in ProjeQtOr's configuration), setting activity to first staus "in progress" doesn't set real start date.
 

I try to create new activity, to change status to "assigned" and come back to "in progress", saving several time, nothing work.

So, i close firefox and restart it and now it works.

I get this starnge issue on several firefox instance (i use several ones to test configuration for several profiles).

Any idea ?

Regards,

 
Attachments:

Please Connexion or Create an account to join the conversation.

More
08 Jan 2025 17:06 #2 by jmmbb
Possible explanation :
when changing PROGRESS in FIXED DURATION MODE, it set to status to the first "in progress" status, but don't set the real start date.

After that, even if i change status to "assigned" and set it another time to "in progress" (even with PROGRESS set to 0), it doesn't change anymore.
I need to restart ProjeQtOr screen by logging out.

Please Connexion or Create an account to join the conversation.

More
08 Jan 2025 17:24 - 08 Jan 2025 17:25 #3 by jmmbb
In fact, it is not systematic...
I got one activity that doesn't change anymore....
Even if i change it to "done"...
 

Nothing in firefox's log....
Nothing in ProjeQtOr's log
Attachments:
Last edit: 08 Jan 2025 17:25 by jmmbb.

Please Connexion or Create an account to join the conversation.

More
08 Jan 2025 17:34 #4 by babynus
Hi,

I don't understand your description

when changing PROGRESS in FIXED DURATION MODE, it set to status to the first "in progress" status, but don't set the real start date

You mean you have Fix Duration Activity, manual progress enabled, you enter Progress > 0% and it changes the status ?
I don't get this behaviour, and don't remember about automation that sets the status from progress. 

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
09 Jan 2025 09:28 #5 by jmmbb
Yes, this is the normal behaviour and requested as this when we sponsoring the manual progress.
It works fine but "in progress" date is not set and real start date is not set anymore.

Please Connexion or Create an account to join the conversation.

More
09 Jan 2025 09:30 - 09 Jan 2025 10:17 #6 by jmmbb
I make some new tests and get an error with no message (just red popup), nothing in log (???) and i lost 8 on 9 activities...
I investigate in the database...

Problem found, nothing from ProjeQtOr, forget this reply :) !
Last edit: 09 Jan 2025 10:17 by jmmbb.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.074 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.