View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Report "List of works for an activity" don't use "unit for workload" hours - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

15 et 16 avril 2025 (9h-12h30)

14 et 15 mai 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

23 et 24 avril (9h-12h30)

20 et 21 mai (9h-12h30)

 

 

 

Report "List of works for an activity" don't use "unit for workload" hours

More
15 Jan 2025 11:11 - 15 Jan 2025 11:11 #1 by davide.miccone@gmail.com
I run the report "List of works for an activity" for half hours activity (0.5h) that I put in "Dispatch work"
The report display 0.0625 h instead of 0.5 h

Seems that global settings "unit for workload" is not considered

version 12.0.0
Last edit: 15 Jan 2025 11:11 by davide.miccone@gmail.com.

Please Connexion or Create an account to join the conversation.

More
15 Jan 2025 16:49 #2 by Irma
Good morning Projeqtor team,
We have just updated Projeqtor, and I noticed the new feature that allows adding specific comments on the hours entered in the Timesheet. This is extremely useful for us: thank you. I also saw the report "List of works for an activity", which shows these details. However, I have a problem: our work unit is set to hours, but the report seems to be based on days. I’m attaching a couple of screenshots to illustrate the issue. Thank you again for your work and support.

davide.miccone@gmail.com post=38337 wrote: I run the report "List of works for an activity" for half hours activity (0.5h) that I put in "Dispatch work"
The report display 0.0625 h instead of 0.5 h

Seems that global settings "unit for workload" is not considered

version 12.0.0

Attachments:

Please Connexion or Create an account to join the conversation.

More
17 Jan 2025 15:39 #3 by babynus
Unit issue on report "List of work for an activity" is already identified on V12.0.0 and fixed.
Fix will be deployed on V12.0.1
Fix is already available through subscirption service.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.041 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.