ProjeQtOr free project management software - Mismatch between totla Expense in project and report expense - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

15 et 16 avril 2025 (9h-12h30)

14 et 15 mai 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

23 et 24 avril (9h-12h30)

20 et 21 mai (9h-12h30)

 

 

 

Mismatch between totla Expense in project and report expense

More
22 Avr 2025 10:22 #1 by FAD
HI,

I'm facing with the following.

On my project, I have a wrong value for expense on project view (See attached file).

The value presented, is not like the value of report expense project (See attached file).

I d'ont undestand where the value 111 862 € is intiated ?

Many thanks for your help, if you have some ideas to help me.

Regards,

Fred

 
Attachments:

Please Connexion or Create an account to join the conversation.

More
23 Avr 2025 11:28 #2 by babynus
Assigned expense is calculated from sum of "planned amount" for all expenses on the project, including Project Expenses, Activity Expenses and Individual Expenses

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: FAD

Please Connexion or Create an account to join the conversation.

More
23 Avr 2025 15:38 - 23 Avr 2025 15:39 #3 by FAD
Thank you Baynus for your reply.

Your explanation was my understanding, but something seems wrong.

All of expense in my project are 0 €. I have just allowed time on activities and in the project summary, I found 111 862 €, this value is strange
Attachments:
Last edit: 23 Avr 2025 15:39 by FAD.

Please Connexion or Create an account to join the conversation.

More
23 Avr 2025 15:59 - 23 Avr 2025 15:59 #4 by FAD
Babynus,

I have tested the following situation.

I have filled the value -111 862 € in project expense, and the value of project expense summary, change to 0 €.
Attachments:
Last edit: 23 Avr 2025 15:59 by FAD.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.041 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.