View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Duration of planning days of activities disagree with the planned hours - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Duration of planning days of activities disagree with the planned hours

More
25 Aoû 2017 14:07 #1 by #Chris
Hello all,
we have a problem with the planning of activities. I created a project with some activites, I said the first activity “Verdrahtung1” will need 30 hours. (As basic settings we have working hours for 6 hours per day.) So normally the program should plan the activity for at least 5 days. But it’s just for one day as you can see in the picture. So the time is too short. When I run the planning nothing changed. Is it a bug or is it my mistake?



Another thing is, when I change the planning in “as soon as possible” the activity starts today although the project has the validated start date 22.08.2018. (But it’s still just one day.) In my understandig activites should only be planned after the validated start date of the project and not before the project starts.

Thanks for your help.
Attachments:

Please Connexion or Create an account to join the conversation.

More
25 Aoû 2017 14:54 #2 by babynus

So normally the program should plan the activity for at least 5 days.

At least 15 days, as you defined rate at 30% (not work more thant 30% of capacity per day).

But it’s just for one day as you can see in the picture.

This is tipical of not really planned project....
When you calculated planning, check that you include the corresponding project.
Also check : allocation to project rate (must not be zero), capacity of resource (must not be zero), "fix planning" on project (must not be checked), and project type (must not be administrative nor template)

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.036 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.