ProjeQtOr free project management software - 'Validated work' reset after assignment - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

'Validated work' reset after assignment

More
23 Nov 2017 17:09 #1 by caccia
Hello,
Issue I've encountered:
- Parameter "consolidate validated work" = 'Always'
- create an activity, validated work = 10d
- add an assignment, assign 1d to team member
=> the validated work becomes 0

I would expect the validated work value to remain 10d (this is on the lowest level of Activity).

Please Connexion or Create an account to join the conversation.

More
25 Nov 2017 02:19 #2 by babynus
Issue confirmed are recorded as Ticket #3100

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.030 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.