ProjeQtOr free project management software - An activity has been completed, but it won't let me close the activity complete - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

An activity has been completed, but it won't let me close the activity complete

More
20 Déc 2017 23:55 #1 by iconic
I have an activity where the real hours equals 4 and the assigned hours in 4 and we there is no left hours, but everytime I try to close the activity it says
"Invalid controls.Unable to close an element with left work"

See attachment as it shows there is 4 hours of work, but we have correctly added the 4 hours on Real Time Allocation.
Attachments:

Please Connexion or Create an account to join the conversation.

More
21 Déc 2017 10:03 #2 by babynus

See attachment as it shows there is 4 hours of work, but we have correctly added the 4 hours on Real Time Allocation.

Hem...
Clearly not.
Your print screen clearly shows :
assigned : 4
real : 0
left : 4

Please post screenshot of real work allocation to see what's wrong.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
21 Déc 2017 11:44 #3 by iconic
Not necessarily. You can see that in assignement, there was 4 hours assigned and 4 hours real and 0 hours left.
See the attachment. Activity is the yellow highlighted area
Attachments:

Please Connexion or Create an account to join the conversation.

More
21 Déc 2017 11:54 #4 by babynus
I agree, this is strange.
There is some unconsistency betwwen assignement (real=4) and activity (real=0)
I cannot explain this, as real on activity is sum of real on assignments...

1) Do you have any errors in log file ?
2) Can you try to make a change in assignement ? (for instance, add 1 hour of left work, save, then revert change to 0 hours left) Does it fox the issue ?
3) which version of projeqtor are you using ?

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
21 Déc 2017 12:11 #5 by iconic

1) Do you have any errors in log file ?

Where do I find this to check?

2) Can you try to make a change in assignement ? (for instance, add 1 hour of left work, save, then revert change to 0 hours left) Does it fox the issue ?

I tried this and it worked and it removed the hours left and displayed it as 0.

3) which version of projeqtor are you using ?

Still using 6.1.2

Please Connexion or Create an account to join the conversation.

More
21 Déc 2017 12:27 #6 by babynus

Where do I find this to check?

Default location is in projeqtor/files/log

I tried this and it worked and it removed the hours left and displayed it as 0.

Great !

Still using 6.1.2

This is not the last patch on V6.1.
You should at least migrate to V6.1.3
But my advise is to migrate to V6.4.4 (every version brings fixings, sometimes to old isues)

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.071 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.