View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - If a user wants additional time to finish a job, let him use "Extra work" column - Page 2 - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

If a user wants additional time to finish a job, let him use "Extra work" column

More
31 Mai 2018 07:59 #7 by NarayanAras
It is OK to give a psychological advantage to the resource in opening up about the extra time needed.

But it has the following disadvantages:
  • It affects the project's timeline without the PM's knowledge/concurrence.
  • It may exceed the resource's allocation period to the project.
  • It will delay the dependent tasks, thus affecting the allocation period of the OTHER resources to the project.
  • The change of allocation period of all resources will lead to delays in OTHER projects as well.

Thus a casually extended task can have three separate domino effects.

In some organizations there is a matrix reporting (resources report to a manager, but get allocated to different projects, sometimes concurrently).

In such cases the extension affects multiple managers: The current PM, the other affected PMs and the resource manager.
All the managers will have to scramble to take corrective measures.

Thus the tool should not allow a junior employee to set off chain of events across the organization.

In such cases the tool cannot leave this to outside communication channels to settle the issue.
The workflow itself must handle the entire issue of extension.

Please Connexion or Create an account to join the conversation.

More
16 Juil 2018 07:43 #8 by NarayanAras
Hi Babynus,

Congratulations on winning the FIFA cup!

If you review the points I made in this thread, you will realize that there are several major advantages of not letting the resources change the Left figure, and several critical advantages for the business if the extension is brought to the attention of the manager.

Could you please bring in any solution that addresses the points I raised?
IMHO an Extra column is the simplest solution.

Please Connexion or Create an account to join the conversation.

More
16 Juil 2018 09:53 #9 by babynus
Request recorded as Ticket #3491
Set at low priority.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
26 Juil 2018 09:02 #10 by NarayanAras
Only a yellow card? I expected a red card (immediate elimination from the game!)

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.036 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.