View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Risk management and planning - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Risk management and planning

More
04 Juil 2019 09:43 #1 by diegobn
Hello,

I would to propose an evolution about risk management, please correct me if I am missing anything or there's something I am wrong about.

When I create a risk I can input the cost of the risk (I input the mitigation costs, and I also input the end date considering the foreseen delay) but I can't see the impact on the planning of the project: if I originate it from a task (e.g. I have an activity going on that can be affected by external factors which could delay it) it could be useful to see the impact in terms both of costs and delay on the task itself.

Besides it could be useful to have a risk management plan like the it was requested with ticket #2540 (2016-0539).

I am aware of the difficulties of implementing such a feature (how am I going to decide whether the impact shall be shown on the gantt diagram or not? And in which percentage? With regards to the risk matrix, which result am I going to accept?) but it's a key feature missing in almost all project management tools available on the market, even proprietaries (and not cheap ones).

Thank you anyway.

Best regards.
The topic has been locked.
More
08 Juil 2019 10:53 #2 by babynus

When I create a risk I can input the cost of the risk (I input the mitigation costs, and I also input the end date considering the foreseen delay) but I can't see the impact on the planning of the project: if I originate it from a task (e.g. I have an activity going on that can be affected by external factors which could delay it) it could be useful to see the impact in terms both of costs and delay on the task itself.

Maybe what you're looking for is provided through "global planning" view.
There you can define dependencies from risk to activity.

Babynus
Administrator of ProjeQtOr web site
The topic has been locked.
More
08 Juil 2019 13:43 - 08 Juil 2019 13:44 #3 by diegobn
I was thinking of something a little more integrated but that will do, thank you very much.

Best regards.
Last edit: 08 Juil 2019 13:44 by diegobn.
The topic has been locked.
Moderators: babynusprotion
Time to create page: 0.035 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.