View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Assign ressource - Page 3 - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

15 et 16 avril 2025 (9h-12h30)

14 et 15 mai 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

23 et 24 avril (9h-12h30)

20 et 21 mai (9h-12h30)

 

 

 

Assign ressource

More
05 Oct 2012 09:34 #13 by babynus
Replied by babynus on topic Re: Assign ressource
Sorry, but I really still dont't undesrstand the need. :dry:

I understand your request, but I would like to be sure to is facing a real need :huh:

In my opinion, you should not assign many resources to single task.
If you do this, possibly it is to define a team, and you still don't know who will work on the activity. Then, maybe you need to define an abstract resource with capacity of 5 or 8 to plan the activity. The resource who really works on it will just as to be defined as responsible to be automatically assigned.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.027 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.