View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Recalculation Auto - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

Recalculation Auto

More
30 Nov 2015 15:24 #1 by El Wallos
Recalculation Auto was created by El Wallos
Hi

It could be a good idea to have a check box to recalculate automaticaly the planning after any update. I think this check box could be useful at project level.

Thanks

Please Connexion or Create an account to join the conversation.

More
01 Déc 2015 08:23 #2 by babynus
Replied by babynus on topic Recalculation Auto
This button already exists in the planning view.
Can be used for instance when you build your project.

To have global calculation on each change, it is a bit more complex than a single button.
But request already exists : Ticket #1815

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
01 Déc 2015 09:36 #3 by El Wallos
Replied by El Wallos on topic Recalculation Auto

babynus wrote: This button already exists in the planning view.
Can be used for instance when you build your project.

Could you give me more detail about this way?

babynus wrote: To have global calculation on each change, it is a bit more complex than a single button.
But request already exists : Ticket #1815


No doubt it is not easy :silly: Your work and your project is awesome.... Thanks again for your help

Please Connexion or Create an account to join the conversation.

More
01 Déc 2015 10:43 #4 by babynus
Replied by babynus on topic Recalculation Auto

Could you give me more detail about this way?

Just go to the planning view, check the checkbox "automatic run plan" and make any change on activity. You'll see what happens.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
01 Déc 2015 15:27 #5 by El Wallos
Replied by El Wallos on topic Recalculation Auto

babynus wrote:

Could you give me more detail about this way?

Just go to the planning view, check the checkbox "automatic run plan" and make any change on activity. You'll see what happens.


I'm working on v5.0.6, is it enable? because i didn't found it.

Please Connexion or Create an account to join the conversation.

More
01 Déc 2015 15:31 #6 by babynus
Replied by babynus on topic Recalculation Auto
No.
New on V5.1

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.045 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.