View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Link between calendar and works days - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

Link between calendar and works days

More
07 Nov 2017 11:08 - 07 Nov 2017 11:12 #1 by adali
First thanks for the great job you do, I would like to suggest to have a link between Works days (in general configuration) and calendar (standard or personalised), for international reason, like that I create days off and time work related to specific calendar,
Thanks & best regards
Aziz
Last edit: 07 Nov 2017 11:12 by adali.

Please Connexion or Create an account to join the conversation.

More
08 Nov 2017 09:39 #2 by babynus
I don't understand your request.
Tool already has "link" : off days defined on global parameters are off days on calendars....

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
08 Nov 2017 10:01 #3 by adali
Yes you're right once we define week end in general parameters we get it in our calendar, but in my case the week end in my country is Friday and saturday, and we have some project in africa where the week end is not the same (saturday and sunday). in this case I create a new calendar bases on standard one, so I get all week end setup in global parameters (Friday and saturday,) and I have to change sunday to exception day off, if the the project take month, I have to do it for all the month
Hope I was clear, my English is not perfect :)

Please Connexion or Create an account to join the conversation.

More
08 Nov 2017 10:09 #4 by babynus
Yes, you're clear.
But there is no alternative.
You must define "default" off days, and if one calendar has different off days you must define then one by one...
There is an improvement planned on this subject (Ticket #2690) but it's not high priority.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
08 Nov 2017 10:20 #5 by adali
Thank you for your answer and happy that I my english was Ok, :) , I hope to see this feature sooner as Projeqtor has an international approche of project management.

Please Connexion or Create an account to join the conversation.

More
08 Nov 2017 10:22 #6 by babynus
Hi,
If you need this evolution sooner, you can concider sonsoring it.
This way you'll contribute to ProjeQtOr improvment and will get you need implemented asap.
Please contact us through contct form if you're interested.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.035 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.