View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - [SOLVED] Incomming planification - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

[SOLVED] Incomming planification

More
08 Avr 2019 14:30 #1 by jmmbb
When associating incomming with milestone, planned date for incomming isn't synchronized with milestone planned date.

I think it will be nice to calculate planned date for incomming with associated milestone instead of reporting manually the new planned date (with delay between incomming planned date and milestone planned date like delay between activity and milestone ?).
The topic has been locked.
More
08 Avr 2019 23:23 #2 by babynus
Replied by babynus on topic Incomming planification
IT can be done.
Just activate the automation in : Menu Global Parameters, Tab Activity, section Automation, parameter "update incoming from milestone"
;)

Babynus
Administrator of ProjeQtOr web site
The topic has been locked.
Moderators: babynusprotion
Time to create page: 0.031 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.